No beach nourishment projects are scheduled to be performed on any Dare County beaches in 2025.
May 2025 Update:
Permitting and design work for the beach nourishment projects scheduled to take place in 2026 in Avon and Buxton are ongoing. Erosion rates are being monitored and will impact the volume of sand that is placed on each beach. Both projects are currently expected to begin in the early summer of 2026. Additional information will be posted once further details are available.
January 2025 Update:
The Dare County Board of Commissioners voted during its January 6, 2025 meeting to authorize Dare County Finance Director David Clawson to sign the Designation of Applicant’s Agent (DAA) and State-Applicant Disaster Assistance Agreement (SAA). These agreements are necessary to apply to receive federal and state funding following loss of sand in the project area in Buxton during Potential Tropical Cyclone #8 last September.
The Federal Emergency Management Agency (FEMA) declared Dare County eligible for disaster assistance due to the storm’s impacts, which resulted in approximately 175,000 cubic yards of sand loss in Buxton. A post-storm survey conducted by Coastal Science and Engineering placed the cost of replacing this sand at $10.2 million. If the funding is approved, the county plans to integrate this effort into its larger 2026 maintenance project, leveraging efficiencies and cost savings.
2022 Buxton Beach Nourishment Project Reports
August 17, 2022: Last Load of Sand in Buxton was Placed on August 16, 2022
August 11, 2022: 90 Percent of the Contracted Volume in Buxton is Complete
August 5, 2022: 60 Percent of the Contracted Volume in Buxton is Complete
August 2, 2022: The Ellis Island has Returned to Assist the Liberty Island in Buxton
July 28, 2022: Buxton Beach Nourishment Operations Have Resumed
July 22, 2022: Buxton Beach Nourishment Remains Paused
July 19, 2022: Buxton Beach Nourishment Paused Until Further Notice
July 18, 2022: Significant Progress on the Avon and Buxton Beach Nourishment Projects
July 11, 2022: Nourished Southern Section of Buxton Beach Nourishment Expected to Open July 12
July 8, 2022: Buxton Beach Nourishment Continuing South
July 5, 2022: Buxton Beach Nourishment Resumed on July 4, 2022
July 2, 2022: Buxton Beach Nourishment Paused Due to Tropical Storm Colin
June 28, 2022: Beach Nourishment in Avon Continues
June 27, 2022: Ellis Island Dredge to Start Pumping in Buxton
June 8, 2022: Projected Dredge Arrival Dates and Project Start Dates
March 24, 2022: Video: Public Meeting at the Fessenden Center in Buxton, NC Regarding Beach Nourishment Projects