Avon Beach Nourishment Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print
A beach nourishment project in the unincorporated village of Avon on Hatteras Island is currently scheduled to take place in May 2026.*

April 16, 2026 Avon and Buxton Beach Nourishment Update:

Dare County’s contractor, Great Lakes Dredge and Dock Company, is planning to start beach nourishment in the Village of Avon, prior to performing beach nourishment in the Village of Buxton. The exact location where they will begin in Avon has not yet been determined by the contractor. Great Lakes expects to start pumping sand onto the beach in Avon between May 6, 2026 and May 14, 2026, depending on weather conditions. 

Great Lakes currently estimates that it will take approximately 2 weeks (14 days) to place approximately 375,000 cubic yards of material on the beaches in Avon (weather dependent). The contactor also expects it to take approximately one week to demobilize all of their equipment and begin moving it to Buxton.

Great Lakes expects to start pumping sand on the north end of Buxton and then continue working south; however, this is subject to change based on their ability to do so. Great Lakes expects to start placing material on the beaches in Buxton the first week of June 2026. Great Lakes expects for the base amount of approximately 1,351,616 cubic yards to take approximately 65 days to place on the beach in Buxton (weather dependent).

If the county receives notification from FEMA regarding additional funding, more material will be placed on the beach, which could extend the project in Buxton until end of September 2026.


Erosion rates are being monitored and will impact the volume of sand that is placed on the beach. Permitting and design work for this project is ongoing. Additional information will be posted as it becomes available.

Click here to sign up for Avon beach nourishment email updates.

*Please note that this information is subject to change. More detailed information regarding any plans and potential schedules for future renourishment/maintenance projects in Dare County will be provided as it becomes available. 


2022 Avon Beach Nourishment Project: 

In 2022, approximately 2.5 miles of shoreline from 3,000 feet north of Avon Pier at Due East Road to the National Park Service Station/Avon Boundary at a construction cost of $11,730,962. The nourishment project began on June 19, 2022, and was completed on June 27, 2022.

Click here to view the 2022 Avon beach nourishment project map.

Avon Beach Nourishment Updates
Side-by-side aerial images of Avon beach photos taken on July 15, 2020 (pre-nourishment) and July 26, 2022 (post-nourishment).
   
Aerial image of the Avon beach nourishment progress, nearing completion.
Aerial image of beach nourishment progress in Avon, looking north. Image courtesy of Coastal Science & Engineering. Photo taken on July 26, 2022.